=='''Africa RISING Phase II <br/>Internally Commissioned External Review <br /> June/July 2019 - June 2020 <br />'''== | =='''Africa RISING Phase II <br/>Internally Commissioned External Review <br /> June/July 2019 - June 2020 <br />'''== | ||
'''Schedule''' | '''Schedule''' | ||
− | *Document reviews: | + | *Document reviews: June/July 2019 (5 days/reviewer) |
*Key informant interviews: June/July 2019 for WA and Ethiopia, January 2020 for East/Southern Africa (2 days/reviewer, 3 days team leader) | *Key informant interviews: June/July 2019 for WA and Ethiopia, January 2020 for East/Southern Africa (2 days/reviewer, 3 days team leader) | ||
*Travels to countries to meet with key informants and field visits: September 2019 (Ghana and Mali); October 2019 (Ethiopia), February/March 2020 (Zambia, Malawi, Tanzania);a detailed schedule will be worked out by Africa RISING Management (# of days to be determined after finalizing the schedule) approx. 10 days per project per reviewer | *Travels to countries to meet with key informants and field visits: September 2019 (Ghana and Mali); October 2019 (Ethiopia), February/March 2020 (Zambia, Malawi, Tanzania);a detailed schedule will be worked out by Africa RISING Management (# of days to be determined after finalizing the schedule) approx. 10 days per project per reviewer |
Revision as of 03:38, 30 April 2019
Africa RISING Phase II
Internally Commissioned External Review
June/July 2019 - June 2020
Schedule
- Document reviews: June/July 2019 (5 days/reviewer)
- Key informant interviews: June/July 2019 for WA and Ethiopia, January 2020 for East/Southern Africa (2 days/reviewer, 3 days team leader)
- Travels to countries to meet with key informants and field visits: September 2019 (Ghana and Mali); October 2019 (Ethiopia), February/March 2020 (Zambia, Malawi, Tanzania);a detailed schedule will be worked out by Africa RISING Management (# of days to be determined after finalizing the schedule) approx. 10 days per project per reviewer
- Interim report with key findings and draft recommendations for WA and ET projects: November 2019 (8 days/reviewer, 10 days team leader)
- Debriefing meeting with PCT: could be virtual, March 2020 after conclusion of field trips in Tanzania (1 day)
- Draft report writing: April 2020 (10 days/reviewer, 12 days for team leader)
- Feedback on draft report from PCT: May 2020
- Final Report writing: two weeks after receipt of feedback from PCT (June 2020) 2 days/reviewer, 4 days for team leader)
Deliverables
- Initial summary report on the findings (for the debriefing meeting)
- Interim report for WA and ET projects
- Draft report with key findings and recommendations - for comments and feedback by the Africa RISING PCT
- Final report with key findings and recommendations (no more than 50 pages)
Program background materials
- Program Phase II proposal
- Program data management plan: 2019–2021
- | Program communication and knowledge management strategy: 2019–2021
- | Peer reviewed journal publications
- | Phase I program framework: 2012 - 2016
Project background materials
Previous internally-commissioned review reports
General resources for the reviewers:
- | CGspace outputs repository
- | AR web site and updates
- AR data portal